Type Request for Bid - Informal - Construction
Status Issued
Number RFB FY2024 #174 Addendum 2 (White Oak Stair Material Replacement)
Issue Date & Time 9/21/2023 01:00:03 PM (CT)
Close Date & Time 10/20/2023 01:00:00 PM (CT)
Notes We highly recommend online submission of responses. This expedites the process and reduces errors for both buyer and supplier.

If you are not yet a registered supplier in ION Wave, please click this link https://iowadotebid.ionwave.net/Login.aspx to register for participation and full access to all documents.

Overview: The Iowa Department of Transportation is seeking bids for White Oak Stair Material Replacement at the Iowa Department of Transportation's White Oak Building located at 800 Lincoln Way, Ames, IA 50010.
*Addendum 1: Bid close and question cutoff extended due to scheduling conflict.
*Addendum 2: Added White Oak Stairs Addendum 2 to Attachments tab. Please review for additions to Scope of Work.
Scope: Remove existing vinyl material and nosing. Replace with new riser and tread vinyl materials specified below. Prepare surface after removal for new material per manufacturer’s specifications. Follow manufacturer instruction for installation. Glass stair railing and wood stringer to remain in place, take care not to damage as much as possible. Field verify all dimensions prior to installation. Submit product information prior to order of materials and provide samples for color selection. Installation to be done during regular working days and hours M – F 8:00 – 4:30.

Award: It is the intent of the Iowa DOT to award the contract to the responsible bidder whose submitted quotation is the most advantageous to the Iowa DOT, cost and other factors considered. Other factors include, but are not limited to: Meeting or exceeding mandatory requirements, proposed staffing, and meeting required time schedule.

Questions: All questions related to this project are to be submitted through the ION Wave Bid system on or before the cut off date and time as indicated in the solicitation.

Estimated start date -11/01/2023 ( The date shall be coordinated with the IDOT Project Manager. (This is the estimated start date after all required documents are received (i.e., Insurance, performance bond and vendor signed contract).

Estimated project end date- 02 /01/2024 (This includes re solution to all punch list items, inspections and DOT acceptance typically used in construction bids).

C ontractor is required to provide all materials, equipment and labor for the removal and replacement of material as per plans/specifications outlined on the Line Item tab. This includes the disposal of all debris off site.

Site Visits: A site visit is recommended to verify measurement and will be accommodated if needed prior to submitting a bid to ensure the vendor has access to view the job site. To schedule a site visit, contractors must contact the Purchasing Agent overseeing the bid at kyle.williams@iowadot.us with a date and time of when you want to conduct a site visit.

Please schedule and conduct all site visits prior to October 6, 2023. Contractors will be required to bring their own equipment needed for the site visit.

Davis-Bacon wages do not apply.

Contact Information
Name Kyle Williams
Address 800 Lincoln Way
Ames, IA 50010
Phone (515) 233-7960
Fax
Email kyle.williams@iowadot.us

TRY FOR FREE

Not a USAOPPS Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >