Project Description: The Public Improvement, upon which bids are requested, generally consists of bridge rehabilitation located at the 16th Avenue, F Avenue, and E Avenue Bridges. The Engineer’s estimate of probable cost is $2,670,000.
Early Start Date: Overall - Upon Receipt of Notice to Proceed
16th Avenue Bridge - Upon Receipt of Notice to Proceed
E & F Avenue Bridges - Upon Receipt of Notice to Proceed, unless USACE closure has not commenced
Late Start Date: Overall - 04/01/2024
16th Avenue Bridge - 04/01/2024
E & F Avenue Bridges - 04/01/2024
Milestones: None
Final Completion: Overall: Completion Date - 11/27/2024
16th Avenue Bridge: Working Days - 58
E & F Avenue Bridges: Working Days - 115