Agency: |
Iowa State University |
Level of Government: |
State & Local |
Category: |
- 99 - Miscellaneous
- N - Installation of Equipment
- Y - Construction of Structures and Facilities
|
Opps ID: |
NBD18079692831381246 |
Posted Date: |
Jan 27, 2023 |
Due Date: |
|
Solicitation No: |
1000690 Addendum 1 |
Bid Information
Type
|
Request for Quote (Public)
|
Status
|
Awarded
|
Number
|
1000690 Addendum 1 (Memorial Union Interior Refinement and Wayfinding)
|
Issue Date & Time
|
12/21/2022 04:00:01 PM (CT)
|
Close Date & Time
|
1/13/2023 04:00:00 PM (CT)
|
Duration
|
22 days 23 hours 59 minutes 58 seconds
|
Notes
|
Iowa State University of Science and Technology (ISU) is soliciting information from qualified companies to provide and install wayfinding and branding signage inside of the Memorial Union.
Companies should read all materials carefully and note the due date.
Companies must submit all questions in the "Questions" tab related to this bid opportunity.
|
Contact Information
Name
|
Matthew Linder
|
Address
|
1340 Administrative Services Building
2221 Wanda Daley Drive
Ames, IA 50011-1004 USA
|
Phone
|
(515) 294-2834
|
Fax
|
|
Email
|
mjlinder@iastate.edu
|
|
Bid Questions
Question
|
With regards to the History Wall, how are the seams in the existing wall handled? What is the plan for the existing thermostat and fire alarm?
|
Answer
|
The seams line up with the graphics. The fire alarm horn strobe will need to stay as is, but the thermostat may be moved. Companies are to bid as specified. The potential moving of the thermostat can be discussed after the project is awarded.
|
Submitted
|
1/10/2023 08:49:10 AM (CT)
|
|
|
Question
|
How are the walls finished?
|
Answer
|
Walls will be Level 4 finish, primed.
|
Submitted
|
1/10/2023 08:44:58 AM (CT)
|
|
|
Question
|
I have been able to locate one company that can do this and received a quote. The company informed me that overlaminates on the vinyl detract from the glow of the product. They recommend using a dreamscape wallcovering with no laminate. Is this substitution approved?
|
Answer
|
Companies should bid as specified. Potential substitutions can be discussed after the project is awarded.
|
Submitted
|
1/6/2023 08:28:46 AM (CT)
|
|
|
Question
|
Currently some of the prints (the square cut ones) call out a MacTac Laminate. This is what is known as a calendar material. (basically standard) The bid requests it to be installed onto 3M 180-10cv3 vinyl. This is what is known as a cast vinyl (premium). We do not mix calendar vinyl and cast vinyl. The lamination will separate from the vinyl and ruin both. Talking to three other printing companies, they have told us the same thing.
Therefor we will not be quoting the MacTac vinyl but rather substituting a different one we will call out in out quote. Is this approved?
|
Answer
|
Companies should bid as specified. Potential substitutions can be discussed after the project is awarded.
|
Submitted
|
1/6/2023 08:27:18 AM (CT)
|
|
|
Question
|
Is there a certain type of wood or stain finish you would like for the 3rd & 4th floor photo bubble walls?
|
Answer
|
At this point, the wood and stain choice is simply "visual pleasing". ISU is not looking for any specific exotic wood.
|
Submitted
|
1/5/2023 10:59:09 AM (CT)
|
|
|
Question
|
Would you be willing to use alternative laminates & adhesive vinyls specified in the bid to reduce costs?
|
Answer
|
Companies should bid as specified. Potential cost saving opportunities can be discussed after the project is awarded.
|
Submitted
|
1/5/2023 10:47:58 AM (CT)
|
|
|
Question
|
The laminate choices and brands do not match with the specified 3M vinyl, which may cause installation and warranty issues. Is there a specific reason these laminates were chosen?
|
Answer
|
The laminates and vinyl have been extensively proven to work very well together. The MacTac Perma Flex 6300 Lamination works very well with the 3M ControlTac IJ180CV3 on wall murals and has a finish that is pleasing. The Arlon 3220 Overlaminate works very well with the 3M ControlTac IJ180CV3 and is easter to cut and weed on contour cut graphics.
|
Submitted
|
1/3/2023 03:14:38 PM (CT)
|
|
|
Question
|
Which specific 3M ControlTac are you looking to have installed? 40C? 180Cv3? there are others as well. Is there a specific product line you are looking to have?
|
Answer
|
3M ControlTac IJ180CV3, please.
|
Submitted
|
12/30/2022 10:13:11 AM (CT)
|
|
|
Question
|
For CYBowl South Entrance Billboard, the SEG fabric graphics is called out to be illuminated. Is the illumination to be supplied as part of this quote? Will Facilities Management be responsible for getting primary electrical to the location, or does the quote need to include the cost of an electrician pulling power to the location?
|
Answer
|
The illumination will be supplied as part of the quote. The electrical will terminate in a 4ft whip. Facilities maintenance will handle the electrical connection.
|
Submitted
|
12/30/2022 09:35:43 AM (CT)
|
|
|
Question
|
There are two different vinyl laminates that are called out for this project from two different manufactures. What is the intention behind the different laminates?
|
Answer
|
The MacTac Perma Flex 6300 Lamination is used for vinyl wallpaper murals where there is no contour cutting. The Arlon 3220 Overlaminate is used on vinyl applications that are contour cut.
|
Submitted
|
12/30/2022 09:32:04 AM (CT)
|
|
|
Items 1 - 10 shown of 14 • Page 1 of 1 shown
|
First
1
2
>
Last
|
Bid Event Participation Activity
|
Activity Date
|
Activity Name
|
Description
|
|
1/5/2023 10:30:00 AM (CT)
|
Pre-Proposal Meeting & Site Visit
|
There will be an optional pre-proposal meeting and site visit due to the nature of this RFP/RFQ. The location of this meeting will begin at the base of the steps inside the west revolving door of the Memorial Union. The Memorial Union is located on the ISU campus at 2229 Lincoln Way.
No verbal statements by ISU or its representatives at this meeting will be binding. ISU will post all changes and material clarifications in the form of an addenda after the meeting. Contractors are strongly encouraged to attend the pre-proposal meeting. Failure to attend or have representation at the meeting will not result in the Contractor or individual being ineligible to participate in the competitive process.
|
TRY FOR FREE
Not a USAOPPS Member Yet?
Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.