Description of Work:
The project will include replacing 267 LF of guardrail to resist limited collision forces on a retaining wall along Mormon Trek Boulevard near the Highway 1 intersection.
Project Schedule Information:
Specified Start Date: April 17, 2023
Final Completion Date: June 30, 2023
Liquidated Damages: $250 per calendar day
Engineer's Estimate:
$
72,000
Bid Deadline:
3:00 p.m. CST on Wednesday, March 15, 2023
Submit Bids To:
City Clerk's Office
City Hall
410 E Washington Street
Iowa City, IA 52240
Obtain Plans From:
Rapids Reproduction
415 Highland Avenue, Suite 100
Iowa City, IA 522240
Phone: (319) 354-5950
(800) 779-0093
info@rapidsrepro.com
Pre-Bid Meeting:
None